Petitioner B.F. Corporation (BFC) is a corporation engaged in general engineering and civil works construction. Petitioner Honorio H. Pineda (Pineda) is the President of BFC. Respondent Form-Eze Systems Inc. (Form-Eze) is a corporation engaged in highway and street construction.

On 29 August 2006, SM Prime Holdings, Inc. awarded the contract for general construction of the SM City-Marikina mall (the Project) to BFC whereby the latter undertook to supply materials, labor, tools, equipment and supervision for the complete construction of the Project.3 In turn, BFC engaged Form-Eze for the lease of formwork system and related equipment for and needed by the Project. Accordingly, five (5) contracts and two (2) letter-agreements were executed by the BFC, represented by its President Pineda, and Form-Eze, represented by its President, James W. Franklin.

Salient provisions of relevant contracts are shown below.

CONTRACT NO. 1: Contract for the Lease of the Equipment for the Beam and Slab Hardware for the Formwork on SM Marikina Mall Project dated 20 December 2006

Work Specifications
The amount of hardware to be furnished is sufficient to provide 7,000 contact square meters of formwork.

Contract Price
Total contract amount for the equipment: 126,000 contact square meters (equipment to be used) x P225.00/contact square meter (cost per use of the hardware for forming the elevated beam and slab)= P28,350,000.00.

Form-Eze was able to supply deckforms which covered 5,149.85 contact square meters of formworks.

CONTRACT NO. 2: Contract for Stripping and Moving Form-Eze Systems Inc. Equipment from Location to Location on SM Marikina Mall Project dated 20 December 2006

Contract Price
Total contract amount for moving equipment: 126,000 x P50.00/contact square meter (cost for stripping and movement of the equipment, excluding cost of resetting to grade, cleaning plywood surfaces and applying release agent) P6,300,000.00.

On 7 December 2007, the CIAC Arbitral Tribunal rendered a Final Award in favor of Form-Eze.


1.    Under Contract No. 1. May the CIAC Arbitral Tribunal require BFC to pay the full contract price?

No.

To award the full contract price to Form-Eze in Contract No. 1 is tantamount to unjust enrichment. By requiring BFC to pay the full contract price when it only supplied deckforms which covered only 5,149.85 contact square meters of formworks, the CIAC Arbitral Tribunal is essentially unjustly giving unwarranted benefit to Form-Eze by allowing it to earn more than it legally and contractually deserved.


2.    What is unjust enrichment?

There is unjust enrichment under Article 22 of the Civil Code when (1) a person is unjustly benefited, and (2) such benefit is derived at the expense of or with damages to another. The principle of unjust enrichment essentially contemplates payment when there is no duty to pay, and the person who receives the payment has no right to receive it.


3.    BFC and Form-Eze agreed that Contract No. 1 should include a labor guarantee provision, which was not shown in the Contract. What is the proper remedy?

Contract No. 1 should be reformed to include a labor guarantee provision.


4.    What is Reformation?

An action for reform a contract is grounded on Article 1359 of the New Civil Code which provides:

ARTICLE 1359. When, there having been a meeting of the minds of the parties to a contract, their true intention is not expressed in the instrument purporting to embody the agreement, by reason of mistake, fraud, inequitable conduct or accident, one of the parties may ask for the reformation of the instrument to the end that such true intention may be expressed.

x x x x

Reformation is a remedy in equity, whereby a written instrument is made or construed so as to express or conform to the real intention of the parties, where some error or mistake has been committed. In granting reformation, the remedy in equity is not making a new contract for the parties, but establishing and perpetuating the real contract between the parties which, under the technical rules of law, could not be enforced but for such reformation.


5.    What are the requisites for an action for reformation of instrument?

In order that an action for reformation of instrument may prosper, the following requisites must concur: (1) there must have been a meeting of the minds of the parties to the contract; (2) the instrument does not express the true intention of the parties; and (3) the failure of the instrument to express the true intention of the parties is due to mistake, fraud, inequitable conduct or accident.


6.    What is the obligation of BFC under Contract No.2?

Since Form-Eze failed to meet the minimum conditions under Contract No. 1 where the minimum 126,000 contact square meters were not reached, then the forklifts under Contract No. 2 were also not used for a minimum of 126,000 contact square meters.

BFC is liable only to pay the amount proportionate to 92,696.40 contact square meters at P50.00 per contact square meter, the rental rate for the forklifts.

7.    Pineda signed the challenged contracts in his capacity as President of BFC. Should he be impleaded as party to the case?

No.

Section 4 of Executive Order No. 1008 vests jurisdiction on CIAC over disputes disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the dispute arises before or after the completion of the contract, or after the abandonment or breach thereof. Moreover, the party involved must agree to submit to voluntary arbitration. In other words, anyone who is not a party to the contract in his personal capacity is not subject to the jurisdiction of the CIAC. In this case, Pineda signed the challenged contracts in his capacity as President of BFC. There is no indication that he voluntarily submitted himself as a party to the arbitration case.


8.    In this case, may the President be considered as a joint tortfeasor?

No.

The actions of the President cannot be considered as an indicia of bad faith to classify him as a joint tortfeasor in this case.


9.    May the final award of CIAC still be subject to judicial review?

Yes.

To begin, Executive Order No. (EO) 1008, which vests upon the CIAC original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, plainly states that the arbitral award "shall be final and inappealable except on questions of law which shall be appealable to the Court." Later, however, the Court, in Revised Administrative Circular (RAC) No. 1-95, modified this rule, directing that the appeals from the arbitral award of the CIAC be first brought to the CA on "questions of fact, law or mixed questions of fact and law." This amendment was eventually transposed into the present CIAC Revised Rules which direct that "a petition for review from a final award may be taken by any of the parties within fifteen (15) days from receipt thereof in accordance with the provisions of Rule 43 of the Rules of Court." Notably, the current provision is in harmony with the Court's pronouncement that ''despite statutory provisions making the decisions of certain administrative agencies 'final,' the Court still takes cognizance of petitions showing want of jurisdiction, grave abuse of discretion, violation of due process, denial of substantial justice or erroneous interpretation of the law" and that, in particular, "voluntary arbitrators, by the nature of their functions, act in a quasi-judicial capacity, such that their decisions are within the scope of judicial review."


10.  When may factual findings of construction arbitrators be reviewed by the Court?

Factual findings of construction arbitrators may be reviewed by the Court in cases where: 1) the award was procured by corruption, fraud or other undue means; (2) there was evident partiality or corruption of the arbitrators or any of them; (3) the arbitrators were guilty of misconduct in refusing to hear evidence pertinent and material to the controversy; (4) one or more of the arbitrators were disqualified to act as such under Section nine of Republic Act (R.A.) No. 876 and willfully refrained from disclosing such disqualifications or of any other misbehavior by which the rights of any party have been materially prejudiced; (5) the arbitrators exceeded their powers, or so imperfectly executed them, that a mutual, final and definite award upon the subject matter submitted to them was not made; (6) when there is a very clear showing of grave abuse of discretion resulting in lack or loss of jurisdiction as when a party was deprived of a fair opportunity to present its position before the Arbitral Tribunal or when an award is obtained through fraud or the corruption of arbitrators; (7) when the findings of the Court of Appeals are contrary to those of the CIAC, and (8) when a party is deprived of administrative due process.


11.  Is the Final Award of CIAC subject to review by the Court of Appeals?

Yes. The Final Award of CIAC is subject to review by the Court of Appeals.

The Court of Appeals nonetheless is not precluded from reviewing findings of facts, it being a reviewer of facts. By conveniently adopting the CIAC's decision as its own and refusing to delve into its factual findings, the Court of Appeals had effectively turned a blind eye to the evidentiary facts which should have been the basis for an equitable and just award.


Comments

Popular posts from this blog

Asiga Mining Corporation Vs. Manila Mining Corporation and Basiana Mining Exploration Corporation

Marcelo G. Saluday Vs. People of the Philippines G.R. No. 215305. April 3, 2018