Power Sector Assets and Liabitlities
Management Corporation Vs. Sem-Calaca Power Corporation
G.R. No. 204719. December 5, 2016
G.R. No. 204719. December 5, 2016
On December 2, 2009, DMCI transferred all of its rights and obligations
under the APA and the Land Lease Agreement (also called Final Transaction
Documents) to herein respondent SEM-Calaca Power Corporation (SCPC) by entering
into an Amendment, Accession and Assumption Agreement that was signed by PSALM,
DMCI and SCPC.9 Under the agreement, SCPC took over all the rights and
obligations of DMCI under the said documents. SCPC also alleged that on that
same date, it took over the physical possession, operation and maintenance of
the Calaca Power Plant.10
Also on the same date, SCPC started providing electricity to customers
listed in Schedule W of the APA, among which is MERALCO.
Schedule W is partially reproduced hereunder:
SCHEDULE
W
POWER SUPPLY CONTRACTS
POWER SUPPLY CONTRACTS
Part
I: Description of the PSC
|
CUSTOMERS
|
POWER SUPPLY CONTRACT
|
REMAINING CONTRACT VOLUME
as of 26 June 2009 |
|||||
|
Contract Duration
|
Monthly Average
|
||||||
|
|
Effectivity
|
Expiration
|
Energy
(MWh) |
Demand
(kW) |
Energy
(Mwh) |
Demand
(kW) |
Average
(MWh/mo) |
|
Meralco (10.841%)
|
6 Nov 2006
|
25 Nov 2011
|
69,256
|
169,000
|
1,517,414
|
169,000
|
69,256
|
|
PEZA-Cavite
Ecozone
|
26 June 2006
|
25 June 2011
|
34,038
|
55,420
|
623,320
|
80,800
|
24,933
|
|
BATELEC I
|
26 Dec 2006
|
25 Dec. 2010
|
16,450
|
42,000
|
334,586
|
42,000
|
17,610
|
|
Sunpower
Philippines
|
18 Aug 2004
|
17 Aug 2019
|
5,500
|
8,955
|
676,500
|
8,970
|
5,500
|
|
Steel Asia
|
26 Mar 2008
|
25 Dec 2009
|
5,263
|
8,000
|
57,770
|
10,000
|
8,253
|
|
SteelCorp
|
26 June 2009
|
25 Dec 2009
|
2,500
|
8,000
|
15,000
|
8,320
|
2,500
|
|
Puyat Steel Corp.
|
26 Nov 2008
|
25 Nov 2009
|
194
|
1,300
|
3,260
|
2,150
|
543
|
|
ECSCO, Inc.
|
26 Dec 2005
|
25 Dec 2010
|
206
|
450
|
4,445
|
440
|
234
|
|
Lipa Ice Plant
|
26 Jan. 2005
|
25 Jan. 2010
|
220
|
400
|
4,650
|
520
|
245
|
|
BCFTPP Contractor
|
|||||||
|
Semirara Mining
|
NA
|
NA
|
291
|
1450
|
NA
|
NA
|
Actual Consumption
|
|
Pozzolanic
Industries Inc.
|
NA
|
NA
|
11
|
50
|
NA
|
NA
|
Actual Consumption
|
|
TOTAL
|
|
MWh
|
703,506
|
3,236,945
|
129,056
|
||
|
|
|
MW
|
295
|
322
|
|||
Notes:
·
All
figures mentioned above are only indicative and will be based on the
hourly/daily/monthly nominated volume as per average monthly contract level. A
typical hourly customer's load profile for Calaca is demonstrated in the
attached Figure 1 of this Schedule J (sic) (Power Supply Contract).
·
The
special conditions governing the assumption by the Buyer of the assignment of a
portion of the Contract Energy under Meralco TSC are contained in Part II of
this Schedule J (sic) (Power Supply Contract).
xxxx
xxxx
Furthermore, in the event that the
Purchased Assets (sic) is not able to supply the contracted power under the
aforesaid contracts due to the unavailability of coal or other causes, the
Buyer may enter into a back-to-back supply contract with other generators or
buy directly from the market for the deficiency.
Part II: Special Conditions of the
MERALCO TSC
The following conditions, unique to
the MERALCO-NPC contract, shall apply to the assigned portion of the Contract
Energy from the MERALCO TSC.
1. Neither the MERALCO TSC nor any
portion thereof shall be assigned to the Buyer. It is the Contract Energy
specified in part I that is the subject of the assignment.
xxxx
SCPC contends that it is obliged to supply 10.841% of MERALCO's total
requirement but not to exceed 169,000 kW in any hourly interval. However, PSALM
holds a different view and contends that SCPC is bound to supply the entire
10.841% of what MERALCO requires, without regard to any cap or limit.
In its Decision dated July 6, 2011, the ERC ruled in favor of SCPC and
against NPC and PSALM.
1. Explain principles
of contract interpretation under Article 1370
Among the key
principles in the interpretation of contracts is that espoused in Article 1370,
paragraph 1, of the Civil Code, quoted as follows:
Art. 1370. If the
terms of a contract are clear and leave no doubt upon the intention of the
contracting parties, the literal meaning of its stipulations shall control.
The rule means that
the contract's meaning should be determined from its clear terms without
reference to extrinsic facts or aids. The intention of the parties must be
gathered from the contract's language, and from that language alone. Stated
differently, where the language of a written contract is clear and unambiguous,
the contract must be taken to mean that which, on its face, it purports to
mean, unless some good reason can be assigned to show that the words should be
understood in a different sense.
Thus, conversely,
when the terms of the contract are unclear or are ambiguous, interpretation
must proceed beyond the words' literal meaning. Paragraph 2 of the same Article
1370 provides:
If the words appear
to be contrary to the evident intention of the parties, the latter shall
prevail over the former.
2. Explain principles
of contract interpretation under Article 1374
Art. 1374. The
various stipulations of a contract shall be interpreted together, attributing
to the doubtful ones that sense which may result from all of them taken
jointly.
Then, case law is
also settled on the rule that contracts should be so construed as to harmonize
and give effect to its different provisions. The legal effect of a contract is
not determined alone by any particular provision disconnected from all others,
but from the whole read together.
3. When may a contract
be considered ambiguous?
A contract
provision is ambiguous if it is susceptible of two reasonable alternative
interpretations. In such case, its interpretation is left to the court, or
another tribunal with jurisdiction over it.
4. Define
Interpretation
More simply,
"interpretation" is defined as the act of making intelligible what
was before not understood, ambiguous, or not obvious; it is a method by which
the meaning of language is ascertained. The "interpretation" of a
contract is the determination of the meaning attached to the words written or
spoken which make the contract.
5. Determine if there
was an ambiguity in Schedule W in this case
The ambiguity in Schedule
W partly lies in the figure "10.841%," which lacks a base value and
is bereft of any specific quantity or number (in kilowatts or any other unit)
to represent the generated electricity that SCPC was obliged to deliver to
MERALCO. A mere percentage below MERALCO's name without indicating what it is
and what its base value is amounts to an incomplete numerical statement. Then,
on the right columns, specific quantities, including the "160,000
kW," are laid down which seem to correspond or add up to SCPC's generating
capacity but which, in the "Notes" section of the schedule, are
confusingly referred to as merely "indicative," i.e., estimates,
which do not help reduce the uncertainty.
Such a lack of
clarity results in a perplexing situation wherein the obligation to deliver
could be interpreted as open-ended by one party — the obligee, but could be
argued as "capped" or "limited" by the other party — the
obligor. Obviously, such divergence needed to be addressed by a disinterested third
party like the ERC.
6. How does the Court
treat rulings of administrative agencies?
It is general
practice among the courts that the rulings of administrative agencies like the
ERC are accorded great respect, owing to a traditional deference given to such
administrative agencies equipped with the special knowledge, experience and
capability to hear and determine promptly disputes on technical matters.
Factual findings of administrative agencies that are affirmed by the Court of
Appeals are generally conclusive on the parties and not reviewable by this
Court. Although there are instances when such a practice is not applied, such
as when the board or official has gone beyond its/his statutory authority,
exercised unconstitutional powers or clearly acted arbitrarily without regard
to its/his duty or with grave abuse of discretion, or when the actuation of the
administrative official or administrative board or agency is tainted by a
failure to abide by the command of the law, none of such instances obtain in
the present case which would prompt this Court to reverse the findings of the
tribunal below.
7. May the court
interfere with the actions of administrative agency?
As such, the Court
will not interfere with the same, mindful of the principle that actions of an administrative
agency may not be disturbed nor set aside by the judicial department sans any
error of law, grave abuse of power or lack of jurisdiction, or grave abuse of
discretion clearly conflicting with either the letter or spirit of the law.
Comments
Post a Comment